QUEENS GATE MEWS, SW7

This project involved construction of a basement to the property's footprint, with a very high end finish.


Key statistics

  • Basement size – 75m²
  • Basement ceiling height – 2,900mm
  • Project Duration – 35 Weeks
  • Property Status – Property vacant for duration of works


Summary of works

  • Construction of secure hoarding to property
  • Demolition of ground floor slab
  • Construction of new ground floor slab
  • Construction of basement to property footprint
  • Installation of waterproof membrane including sumps and pumps
  • Installation of underfloor heating & screed


"I have worked with Noble on numerous projects to date and have found them to be thoroughly professional in regard to all aspects of their work. They always endeavour to complete projects within the contract programme and on budget. Their health and safety is of the highest standards as is their execution of each temporary works design, architectural and structural schemes."